Encuesta regional de salarios
1.1 PP Line: Define, Measure and Analysis 06/04/2010 14/04/2010
1.1.1 Develop VSM: Current & Future J. Lavayen/ A. Khare 06/04/2010 07/04/2010
1.1.2 Capacity Analysys & Simulation J. Lavayen/ A. Khare 09/04/2010 12/04/2010
1.1.3 Materials Flow Analysis A. Almonte/J. Lavayen 13/04/2010 14/04/2010
1.1.4 Place order of Bins in the system J. Marte 14/04/2010 14/04/2010
1.2 PP Line: Improvement and Control 22/04/2010 07/05/2010
1.2.1 APQP for PP (Develop FMEA & Control Plan J. Marte/J. Ciprian 22/04/2010 23/04/2010
1.2.2 Update Change in the Systems J. Marte 26/04/2010 30/04/2010
1.2.2.1 Single work order J. Marte/ F. Peguero 26/04/2010 27/04/2010
1.2.2.2 SOPs & other documents J. Marte